PROJECTS

Windsor Charter Academy Expansion

The Need

Windsor Charter School currently has one gymnasium to serve both middle and high school levels. By adding gym space, the middle and high school will each have their own gym. New classrooms and learning spaces will provide students with additional course options and expanded learning opportunities.

Highlights

The proposed Firebird Facility will include a gymnasium and locker rooms, as well as three classrooms.

  • 37,351 sq. ft.

  • 150 additional student capacity

  • Gymnasium with training spaces

  • 3 classrooms

  • Staff offices

Location


Impact

  • Additional 150-student capacity


Est. Costs

  • $13,069,956 construction costs

  • $4,930,015 soft costs

Est. Timeline

  • Construction Start: June 2023

  • Completion Date: August 2024


Status

  • Executing the contractor selection process. Look to have the final contractor selected in May 2023.

  • Completing design to the Construction Documents level and anticipate completion of the "CD" drawings in March 2023.