Windsor Charter Academy Expansion
The Need
Windsor Charter School currently has one gymnasium to serve both middle and high school levels. By adding gym space, the middle and high school will each have their own gym. New classrooms and learning spaces will provide students with additional course options and expanded learning opportunities.
Highlights
The proposed Firebird Facility will include a gymnasium and locker rooms, as well as three classrooms.
37,351 sq. ft.
150 additional student capacity
Gymnasium with training spaces
3 classrooms
Staff offices
Location
Impact
Additional 150-student capacity
Est. Costs
$13,069,956 construction costs
$4,930,015 soft costs
Documents
Est. Timeline
Construction Start: June 2023
Completion Date: August 2024
Status
Executing the contractor selection process. Look to have the final contractor selected in May 2023.
Completing design to the Construction Documents level and anticipate completion of the "CD" drawings in March 2023.