Severance High School Addition

The Need

The growth in the Severance and West Greeley area has greatly increased enrollment at Severance High School. SHS had nearly 900 students at the start of the 2022-23 school year, exceeding its capacity of 800 students.

Highlights

The school was constructed with growth in mind, with the ability to add additional wings or "pods" over time. This addition would include expanding the school to accommodate an additional pod.

  • 39,000 sq. ft.

  • 1,200-student total school capacity

  • 17 classrooms, including flexible learning spaces and science labs

  • Additional collaboration spaces, teacher work rooms, and conference rooms

Location


Impact

  • Additional 476-student capacity, reducing capacity challenges


Est. Costs

  • $18,014,750 construction costs

  • $3,602,950 soft costs

Est. Timeline

  • Construction Start: August 2023

  • Completion Date: Fall 2024


Status

  • Conceptual Design