ADDITIONAL PROJECTS
Approved Allocation of Contingency Funds
The Process
Among its other oversight charges, the Bond Oversight Committee also evaluates the 2022 Bond program’s contingency fund balance and allocates funds for additional projects with that balance. The committee works hand-in-hand with staff to identify capital project needs from across the district for funding consideration — from security window film and HVAC repairs, to ADA upgrades and parking lot repairs.
We are fortunate to have a healthy contingency fund balance due to project cost savings, premium, and interest. Two important things to note about contingency funds:
We are required by law to use those funds in a defined time period.
We are required by law to use the funds on capital projects.
When reviewing projects, the committee thoughtfully discusses each project, prioritizing the use of project contingency funds towards direct-student-impact projects.
Additional Bond Projects
Grandview Elementary Boiler Replacement ($192,478) — Replacement of failing boiler units.
Estimated Timeline: Fall 2024
Status: Complete
WHS Mechanical ($450,000) — Replacement of aged mechanical units and investigation of the addition of cooling to the gym.
Estimated Timeline: Summer 2025
Status: Design complete
Mountain View Elementary Mechanical ($1,700,000) — Replacement of aged mechanical units.
Estimated Timeline: TBD
Status: Discovery and planning
SHS Softball / Baseball Plaza Seating - ADA ($2,000,000) — Create a plaza between the softball and baseball fields in order to make the fields and seating more accessible per the Americans with Disabilities Act.
Estimated Timeline: TBD
Status: Design
SHS Culinary Modular Move to WHS ($950,000) — Relocation of the SHS culinary modular to the WHS campus, including the detachment and reattachment of unit sections, transportation, plumbing, mechanical, and fire suppression systems.
Estimated Timeline: March 2025 - Summer 2025
Status: Design
SHS Wood Shop Renovation to Construction Trades Lab ($500,000) — Renovation of the existing wood shop to accommodate a more comprehensive construction trades certification program.
Estimated Timeline: March 2025 - Summer 2025
Status: Design
SMS Roof Replacement ($1,929,224) — Replacement of the entire roof while the addition is under construction, so the building has one continuous roofing structure.
Estimated Timeline: Summer 2024 - Summer 2025
Status: Construction underway
Skyview Elementary Mechanical ($750,000) — Replacement of aged mechanical units.
Estimated Timeline: TBD
Status: Discovery and planning
Skyview Elementary Roofing ($75,000) — Replacement of the roof.
Estimated Timeline: May 2025 - Summer 2025
Status: Bidding
Tozer Primary Roofing ($750,000) — Replacement of the roof.
Estimated Timeline: May 2025 - Summer 2025
Status: Bidding
Tozer Primary Playground Equipment - ADA ($175,000) — Installation of additional inclusive exterior playground equipment, including a wheelchair accessible merry-go-round and pour-in-place surface.
Estimated Timeline: Fall 2024
Status: Installation over Winter Break
Tozer Primary Mechanical ($2,000,000) — Replacement of aged mechanical units.
Estimated Timeline: TBD
Status: Discovery and planning
Window Security Film ($1,000,000) — Addition of security film in strategic locations to strengthen glass, making it less penetrable and increasing security on all campuses.
Estimated Timeline: Ongoing
Status: Design
WMS Modernization ($10,000,000) — Enhancement of the learning environment, bringing the school closer to the updated standards that currently exist at RMS and SMS.
Estimated Timeline: Fall 2024 - Fall 2026
Status: Design
WHS Stadium Entrance Apron - ADA ($250,000) — Refinishing the existing stadium entrance to provide a more accessible surface and to improve the general safety of the entranceway, per the Americans with Disabilities Act..
Estimated Timeline: Summer 2025
Status: Design
WHS Stadium Fence ($155,450) — Replacement of the fence surrounding the stadium field and a remodeled ticketing entrance, enhancing the security of the stadium complex and helping to maintain the new field.
Estimated Timeline: Summer 2024
Status: Complete
District Office Expansion ($15,000,000) — Expansion to provide adequate conditions for staff working to support districtwide functions (i.e., instructional support, technology, finance, and human resources).
Estimated Timeline: March 2025 - December 2025
Status: Design