New Elementary Schools
The Need
Our elementary schools range from 102% to 130% core building capacity.
Highlights
Two new elementary schools are planned for the RainDance and Peakview neighborhoods. The Design Advisory Committee worked with the architects to develop a districtwide prototype that will accommodate 600 students, with a target of 24-25 students per class.
75,000 sq. ft.
600-K-5 student capacity and 64-preschool student capacity
100-student Small Learning Communities (SLCs), stacked two stories, that include student gathering space, technology resources, and teacher workrooms / support offices
Centralized Media Hub and STEM Laboratory
Fitness / wellness, music / stage, and cafeteria that are close in proximity to promote afterhour use and to be used as central social gathering locations for students
Teacher workrooms and administrative support offices
Locations
Impact
Additional 600-student capacity per school
Relieves capacity challenges at existing schools
Est. Cost (Each)
$35,701,870 construction budget
$34,649,257 construction guaranteed maximum price (Hollister Lake Elementary)
$36,408,448 construction guaranteed maximum price (Orchard Hill Elementary)
Est. Timeline - Hollister Lake Elementary
Construction Start: April 2023
Move-In: June 14, 2024
Est. Timeline - Orchard Hill Elementary
Construction Start: April 2023
Move-In: July 29, 2024
Status
Hollister Lake Elementary
Complete
Orchard Hill Elementary
Complete
Architect: DLR
CMGC: Adolfson & Peterson Construction