PROJECTS
Existing Building Repairs & Replacements
The Need
In addition to capacity challenges, many of our buildings require significant repairs that are beyond our annual budget.
Highlights
The proposed projects touch schools across the district, extending the buildings’ lives, reducing energy costs, and upgrading security and safety items. These are items identified by our Maintenance & Operations team as high priority.
Districtwide Safety and Security ($7.1M)
External door access control
Public address system upgrade
Internal / external security cameras
Windsor Middle School ($5.3M)
Extend the building's useful life through replacements of the roof, roof-top units, boilers, and water heaters.
Priority 1 Repairs ($4.8M)
Skyview School of STEM: Boiler replacement and cafeteria roof-top unit replacement
Tozer Primary School: Kitchen floor replacement
Windsor High School: Replacement of the roof-top units and roof sections
Priority 2 Repairs ($1.3M)
Windsor High School: Replacement of the stadium turf field and shock pad
Board Approves Additional Repair Projects
The Board of Education approved the Bond Oversight Committee's recommendation to add the following repair and replacement projects within the scope of the 2022 Bond program. The addition of these projects were made possible through project management cost savings to date, as well as bond premium funds.
Grandview Elementary School Boiler Replacement ($192,478) — One of two boilers at the school experienced a catastrophic failure. Both boilers are 20 years old and original to the school's construction in 2004. The committee requested and the Board approved funds to replace both boilers.
Severance Middle School Roof ($1,929,224) — The committee requested and the Board approved the replacement of the entire roof while the addition is under construction, so the building has one continuous roofing structure. This will reduce future maintenance and provide a 30-year warranty. The cost estimate includes design, inspection, materials / labor, installation, and contingency. This project will be divided into two phases, with a portion of the replacement to be completed over the summer of 2024 and the rest to be completed the summer of 2025.
Windsor High School Fence ($155,450) — The committee requested and the Board approved the replacement of the fence surrounding the stadium field and a remodeled ticketing entrance. This will enhance the security of the stadium complex and help to maintain the new field. This project is funded by savings allocated from the turf replacement project.
Impact
Expand the useful life of existing buildings
Reduce operating costs
Enhance school safety and security
Est. Costs
Initial Estimated Cost: $18,500,000 approximately
Bond Oversight Committee and Board-Approved Additional Cost: $2,277,152
Documents
None
Est. Timeline
Safety and Security: Summer 2023 - Summer 2024
Skyview School of STEM Mechanical: Summer 2024
Tozer Primary School Kitchen Floor: June 2023 - August 2023
WMS Roof / Mechanical: Summer 2024 - Summer 2025
WHS Roof / Mechanical: Summer 2024 - Summer 2025
WHS Stadium Turf: May 2023 - August 2023
WHS Stadium Fence: Summer 2024
Grandview Elementary School boiler: Fall 2024
SMS Roof: Summer 2025
Status
Safety and Security: Camera and Public Address System Updates Complete
Skyview School of STEM Mechanical: Complete
Tozer Primary School Kitchen Floor: Complete
WMS Roof / Mechanical: Engineering design
WHS Roof / Mechanical: Engineering design contract awarded
WHS Stadium Turf: Complete
WHS Stadium Fence: Complete
Grandview Elementary School Boiler: Contract awarded
SMS Roof: Construction underway